Colac's
Ambulance Station was relocated to a new site in
Rae St on |
||||
|
Week 1 16 June 2003 Block of land purchased and fenced off in preparation of construction. |
|
|
|
Week 2
23 June 2003 Site Office and building in place. Ambulance Station foundations pegged out. |
|
|
|
Week 3 30 June 2003 Boundary fencing in place. Garage framework up. Foundations for station slab dug. |
|
|
|
Week 4 7 July 2003 Nil progress.
|
|
|
|
Week 5 14 July 2003 Slab laid for station house. Garage framework up. |
|
|
|
Week 6 21 July 2003 Framework for station house walls being erected. Garage roofing in place. |
|
|
|
Week 7 28 July 2003 Framework for station house walls completed. |
|
|
|
Week 8 4 August 2003 Station house roof frame now complete. |
![]() |
|
|
Week 9 11 August 2003 Station house wall insulation wrapping in place. |
|
|
|
Week 10 18 August 2003 Station house roof iron half completed. Brickwork completed below floor line. |
|
|
|
Week 11 25 August 2003 Station roof almost complete. External windows & doors in place. Internal electrical wiring begun. |
|
|
|
Week 12 01 September2003 Garage concrete slab now laid. Some brickwork around station office now complete. |
|
|
|
Week 13 08 September 2003 External brickwork around building now complete. Internal electrical wiring laid throughout the building, awaiting plastering to finish. Work on storm water drainage begun. |
|
|
|
Week 14 15 September 2003 Storm water drainage now complete. Internal plastering begun in wet areas. |
|
|
|
Week 15 22 September 2003 Internal plastering & electrical work continues. Preparation for driveway concreting begins. |
|
|
|
Week 16 29 September 2003 Internal plastering & electrical work continues. All cupboards and kitchen throughout building in place. Garage cladding begins. |
|
|
|
Week 17 6 October 2003 Internal plastering & electrical work continues. Concreting of driveway now complete. |
|
|
|
Week 18 13 October 2003 Painting of branch almost complete. Garage cladding completed. |
|
|
|
Week 19 20 October 2003 Painting now complete. Floor coverings started Landscaping begun. |
|
|
|
Week 20 27 October 2003 Radio tower & wiring completed. Landscaping now finished. Folding doors in place. |
|
|
|
Week 21 3 November 2003 Final week - Handover 10 November. Final finishing and cleanup underway. |
|
|
|
||
|
||
|
||
|
Week 22 12 November 2003 First rostered shift in the new station. |
|
|